Thursday, September 5, 2013

House Update 1.2

The house is coming along nicely at this point. Here is what happened the last half of August.

8.13.13 First floor framed

8.14.13 Second floor framed

8.15.13 Drying in the house...roof on. 

8.17.13 3rd garage bay finally framed.

8.18.13 Checking out the view from the office.

8.21.13 House is plumbed and all bathtubs in place.

Learning Spanish along the way.

8.22.13 Fireplace installed.

8.22.13 Doors installed.

8.22.13 Bricks ready to go on.


8.27.13 I took A LOT of pictures of wires. I'll spare you all those details.

I love going out to the house each night. We see some spectacular sunsets on our way.
This is from our front porch.